In order to upgrade the water supply distribution to meet the increasing water demand in the rapid development of new township along Kuala Baram By Pass in Northern Miri, an 800 mm diameter, 11.2 km pipeline along Pujut-link road and Kuala Baram by-pass road was completed on 2 August 2019 about a month ahead of schedule.

The commissioning was officiated by Ir Franklin Ucar, Chief Executive Officer on 9-Aug-2019. With him are the Management team, Miss Bong Shi Yee, Senior Manager of Human Resource and Administration, Encik Affendi Taher, Senior Manager of Finance, Information Communication and Technology, Miss Liza Raymond, NRW Manager and Encik Zaid Iskandar, Engineering and Planning Senior Executive.



Date: 09 Aug 2019
Venue: Miri